1400 Series
The 1400 Series is a capped and pressure plated unitized panel system. Its controlled fabrication and fast install time make...
The 1400 Series is a capped and pressure plated unitized panel system. Its controlled fabrication and fast install time make...
The 1400-4S Series is a four-sided structural silicone unitized panel system. Its controlled fabrication and fast install time make it...
Our unitized panel systems drastically reduce install time. We bring the majority of the installation time into a controlled envir...
Design-assist and complex unitized curtain wall for Calgary’s iconic New Central Library, delivered over an active LRT and defined by highly complex geometry, 460 unique oversized unitized panels and an Acoustic curtain wall.
LEED: Gold
Calgary’s New Central Library is one of the city’s most recognizable civic buildings, with a distinctive curved form and highly complex building envelope.
Ferguson was brought into the project during the design-assist phase to provide design, engineering and constructibility input, working closely with the design and construction teams to develop and deliver the building envelope solution.
The project required the coordination, fabrication and installation of more than 460 custom unitized panels incorporating more than 6,000 individual glass and composite pieces. BIM integration and detailed 3D modelling were used extensively to coordinate the complex geometry and resolve connections before fabrication and installation.
The building’s complex curved geometry required a high level of precision across the design, engineering, fabrication and installation process. Custom connections and panel configurations had to be developed to accommodate the building’s distinctive form while maintaining performance and constructibility.
A further challenge was the active LRT infrastructure directly below the construction area. Installation had to be carefully phased and coordinated to allow work to proceed safely without disrupting ongoing LRT operations.
The scale and uniqueness of the façade added another layer of complexity, with hundreds of custom unitized panels incorporating thousands of individual glass and composite components.
Ferguson worked collaboratively with the architect, general contractor and project teams from the design-assist phase through completion, providing design input, engineering, constructibility analysis and detailed coordination.
The team used BIM extensively for clash detection and coordination, while custom 3D-modeled connections were developed to achieve precise installation across the building’s complex geometry.
Ferguson supplied and installed the project’s aluminum panel systems, curtain walls and large skylight, including the fabrication and installation of more than 460 custom unitized panels.
Installation was carefully phased around the active LRT infrastructure, allowing the envelope work to progress safely while maintaining uninterrupted transit operations.
Through early coordination and design-assist involvement, potential issues were identified and resolved before they could affect fabrication, installation or the project schedule.
Ferguson delivered the building envelope on schedule and on budget, completing the project over 25 months from design-assist award to substantial completion.
The Calgary New Central Library became a benchmark project for Ferguson’s ability to deliver complex, highly customized unitized envelope systems through integrated design assist, BIM coordination and precise field installation.
Today, the library stands as a monument to the changing face of Calgary. It has received international attention, including from the New York Times, which cited it as one of 2019’s Places To Go.
| Location | Calgary, Alberta |
| Contract type | Design-assist / lump sum |
| Design-assist award | June 2018 |
| Project duration | 25 months, design-assist award to substantial completion |
| Systems | Aluminum panel systems, curtain wall, unitized panels and large skylight |
Design – 6 months
Fabrication – 4 months
Panel Assembly – 4 months
Installation – 11 months
PMU was tested at CRL Miami in November 2014. Report available upon request.